Maintenance Window from 2100 EST through 0300 EST, 7/29 – 7/30. We are finalizing our migration to the new data center. Customers are being moved rack by rack, only the affected racks will be down during the move. Current Status: … Continue reading

Below is a copy of the email that we have emailed to all clients regarding our data center migration next week. Please let us know if you have any questions! As you may have already heard, Razor is growing by … Continue reading

We are pleased to announce that we have turned up our electrical distribution system in the new data center! Our awesome electricians ensured us that everything was hooked up right, then proceeded to “look away from the switch” before flipping … Continue reading

While working hard to finish up our new data center, we have created a promotional video highlighting the neat features of our new digs. Check it out:

Shortly we will be launching our new website. We’re freshening up our look and making information regarding our services easy to access and use. Check out a sneak preview:

Our UPS (Uninterruptable Power Source) has just been turned on and certified by the manufacturer for production use. Our Toshiba G9000 UPS can power our servers in case of a loss of power, at least until our generator kicks in.

The generator that would kick on if the power here ever goes out (which is very rare, we are fed by two distinct power grids) is going through some testing. Let me just tell you that it is LOUD. Well, … Continue reading

Our Dedicated Server Specials have been flying out the door (figuratively speaking) and are almost sold out! Now is your chance to get a great deal on a fast server. We currently have several Dual Intel Xeon E5620 Quad-Core Processor … Continue reading

We are in the process of getting our new data center at 1309 Noble up and running (the HVAC units are up!) and are in the process of building out the redundant power supply inside the floor of the data … Continue reading